DryPack Installation :

  • Remove 8" of dirt for pool deck installation (12” if driveway)
  • Dump and screed 4" of lime-rock for pool deck installation (8” if driveway)
  • Spray DryPack (Base Stabilizer) and rake to go deeper
  • Compact after 15 minutes
  • Mix Portland cement with sand and Anti Hydro and spread 2" thick
  • If using regular small concrete pavers, lay them down then compact as you go;
    If using large format of concrete pavers or natural stone, apply thin-set to the backside of the pavers before laying and compacting them
  • Grout if desired or required
  • Seal with penetrating water base Stone Sealer 70